Indiana GigaPOP Network Operations Report
2019-12-27 - 2020-01-09

Indiana GigaPOP Network Operations Center

Unscheduled Outages Summary

Incident Number Customer Impact Network Impact Title Outage Type Source of Impact Current State Start Time (UTC) End Time (UTC) Duration


Unscheduled Outages Detail


None during this report period


Upcoming Scheduled Maintenances

Ticket No.:CHG0040293
Subject:Maintenance 2 of 2 - Indiana GigaPOP Member Huntington University-Arizona Campus
Source Of Impact: Vendor
Affected:Member Huntington University-Arizona Campus
Start Time:2020-01-17 07:00:00
End Time:2020-01-17 13:00:00
DescriptionMember Huntington University-Arizona Campus will be unavailable while CenturyLink Engineers perform maintenance to replace damaged cable. An outage is expected and the entire window is reserved. Multihomed traffic will reroute. Please note - This is maintenance window 2 of 2.


Ticket No.:CHG0040357
Subject:Maintenance 1 of 2 - Indiana GigaPOP Member University of Notre Dame
Source Of Impact: Vendor
Affected:Member University of Notre Dame
Start Time:2020-01-22 05:01:00
End Time:2020-01-22 10:00:00
DescriptionMember University of Notre Dame should remain available while Peer I-Light's Vendor Zayo performs non-intrusive maintenance to conduct fiber audits in two (2) splice cases. No outages are expected; however, the entire window is reserved. In the event of an unforeseen outage, traffic will reroute via redundant connections. *Please note - This is maintenance window 1 of 2. The second activity date is scheduled for Thursday, January 23, 2020.


Ticket No.:CHG0040292
Subject:Maintenance 1 of 2 - Indiana GigaPOP Member Huntington University-Arizona Campus
Source Of Impact: Vendor
Affected:Member Huntington University-Arizona Campus
Start Time:2020-01-16 07:00:00
End Time:2020-01-16 13:00:00
DescriptionMember Huntington University-Arizona Campus will be unavailable while CenturyLink Engineers perform maintenance to replace damaged cable. An outage is expected and the entire window is reserved. Multihomed traffic will reroute. Please note - This is maintenance window 1 of 2. The second activity date is scheduled for Friday, January 17, 2020.


Ticket No.:CHG0040358
Subject:Maintenance 2 of 2 - Indiana GigaPOP Member University of Notre Dame
Source Of Impact: Vendor
Affected:Member University of Notre Dame
Start Time:2020-01-23 05:01:00
End Time:2020-01-23 10:00:00
DescriptionMember University of Notre Dame should remain available while Peer I-Light's Vendor Zayo performs non-intrusive maintenance to conduct fiber audits in two (2) splice cases. No outages are expected; however, the entire window is reserved. In the event of an unforeseen outage, traffic will reroute via redundant connections. *Please note - This is maintenance window 2 of 2.